Project Background

Insulation work on the bi-annual Shutdown for the PVI inspection of vessels and pipework.

The Solution

The work involved stripping and re-insulating existing pipework and vessels in a 10 week programme. Involving a close working arrangement with the Main Contractor and the Client to ensure that materials and labour were available for the shutdown. A range of specification were required including Foamglass, Nilflam and Mineral Wool.

  • Contract Value: £465,300
  • Construction Period: Ten weeks
  • Year Complete: 2007