Home » Services » Insulation » Thermal Insulation » Case Study
Case Study: Thermal Insulation
- Client: Petrochemical Client
- Project: 2007 Shutdown
- Location: South Wales
Project Background
Insulation work on the bi-annual Shutdown for the PVI inspection of vessels and pipework.The Solution
The work involved stripping and re-insulating existing pipework and vessels in a 10 week programme. Involving a close working arrangement with the Main Contractor and the Client to ensure that materials and labour were available for the shutdown. A range of specification were required including Foamglass, Nilflam and Mineral Wool.
- Contract Value: £465,300
- Construction Period: Ten weeks
- Year Complete: 2007